Fort Meade's Data Center Is Still Waiting on One Thing: Its Water Permit

When people search data centers in Florida water usage, this is the case that shows how the system actually works: the city signed, the land was rezoned, the power track is separate — and the project still cannot proceed until a water management district grants a permit it has not yet granted.

Dark water surface, abstract texture
Illustrative texture image from the site library — never evidence for a claim, a listed business's work, a product, or a measurement.
← Latest briefings

Latest briefing — Sunday, November 22, 2026

Key point: On April 14, 2026, the Fort Meade City Commission voted unanimously (5 to 0) to approve a 20-year development agreement with developer Stonebridge, operating through Fort Meade DC, LLC (limited liability company), for a data center campus of up to 4.4 million square feet on roughly 1,300 acres of former phosphate land west of United States Highway 98 (U.S. 98) in Polk County. That same day, the Southwest Florida Water Management District (SWFWMD) — the regional agency that issues water permits in this part of Florida, often called Swiftmud — wrote to the city that Fort Meade's existing water use permit does not cover the data center, and that approval of a modified permit by the district's governing board is required before the project can be supplied. The project's reported water use is up to 50,000 gallons per day — an estimate, not a permit figure (see the estimate box below). As of this briefing, no issuance of that consumptive use permit (CUP) — the permit that authorizes withdrawing water from an aquifer or a river — has been verified. The permitting queue, not the power queue, is where this project now sits.

What the city actually approved — and what it did not

A development agreement is a land-use and commitments document. It is not a water permit, a building permit, or a guarantee that any other agency will say yes. The April 14, 2026 agreement, as reported from the city's own staff memorandum and the meeting record, does two relevant things: Stonebridge commits to construct certain publicly necessary water and wastewater improvements related to the development, and the City of Fort Meade commits to reserve water and wastewater capacity for the data center. The land itself — west of Highway 98 — had already been rezoned for industrial use in June 2025, and a master development plan had already been approved.

What the agreement could not do is supply the water. In Florida, withdrawing groundwater at scale requires a consumptive use permit from the water management district for that region, under Chapter 373 of the Florida Statutes — the same permit system that governs a city, a farm, and a bottler. That system, and why nobody in Florida owns the water itself, is explained in Who owns the water? The district's April 14 letter made the gap explicit on the day of the vote: the city's then-current permit did not cover this use, and a modified permit would need the district governing board's approval. Reporting in the weeks after the vote added that, under a district policy adopted in December 2025, a data center water permit must be considered by the district's full governing board at a public meeting — not approved quietly by staff — and that as of late April 2026 the developer had not yet applied. Those two details are carried here as reported (see Sources), not as district documents read for this briefing.

The 50,000-gallon figure: an estimate, labeled as one

Estimate — read this box before quoting the number. The figure most often attached to this project is up to 50,000 gallons per day. It is an estimate. It circulates from project documents through local reporting and a city staff memorandum; it was not confirmed from the permit application itself for this briefing, because no issued permit application figure has been verified. Two facts around it are better documented than the number itself. First, the developer revised its request downward during the approval process — from an initial figure reported at 140,000 to 150,000 gallons per day — after pledging a closed-loop cooling system, in which the same water recirculates through sealed pipes and is reused instead of being continually replaced and evaporated. Second, the state questioned the revised figure in writing the day after the city vote: in an April 15, 2026 letter to Fort Meade's mayor, Florida Department of Commerce Secretary J. Alex Kelly wrote that a minimum demand of 50,000 gallons a day "appears woefully underestimated for a 4,400,000 square foot data center," and that the city's approval was contingent on receiving the district's consumptive use permit — in his words, what passed was "far from 'approved.'"

So the honest state of the number is this: 50,000 gallons a day is the developer's revised estimate, the agreement is reported to reserve that amount from the city, and a state agency has said on the record that it looks too low for a campus this size. Anyone quoting it without the word "estimate" is overstating what is known. If a permit is eventually issued, the permit itself — a public district document with a stated quantity — will replace the estimate, and the linked guide will carry the permitted figure: How much water does a data center use?

Putting the estimate on a scale — the arithmetic, shown

Even taken at face value, the estimate is small next to the campuses that drive national headlines — and that is exactly why this fight is about precedent and place, not volume. The comparisons below are computed from stated inputs; because the Fort Meade input is an estimate, every result inherits that label.

Why, then, does a comparatively small number draw a governing-board hearing, a state secretary's letter, lawsuits, and a recall effort (all reported after the April vote)? Because of where the water would come from. Polk County sits in and near the Southern Water Use Caution Area, a roughly 5,100-square-mile region the district designated in 1992 where aquifer levels had already fallen more than 50 feet in places from cumulative permitted pumping, and near the Central Florida Water Initiative planning area, where new industrial and commercial quantities are tightly constrained. A permit granted here becomes the template for the next application. The regional picture is in Is Florida running out of water?

Why the permit — not power — is the binding queue

National coverage usually treats data center siting as a power problem: find the gigawatts, and the project follows. Fort Meade inverts that. Its power track — proximity to Duke Energy's Hines Energy Complex — was a reason the site was chosen, and it proceeds on a separate track. Its land track finished in April. What remains is a water decision that, by design, cannot be rushed: a governing-board vote in public session, under a statute that since July 1, 2026 also bars issuing a large-scale data center permit if the use is harmful to the water resources of the area, and that treats any later modification as a fresh application. A water permit is also unlike a zoning approval in one crucial way: it is issued for a term, it must be renewed, and it can be reduced at renewal or revisited if the use interferes with existing legal users. The district is not being asked to bless the project once, forever — it is being asked to allocate a stressed aquifer, on the record, with everyone watching.

There is a second, quieter connection worth naming. This campus would rise on former phosphate land — mined, reclaimed, and long short of a next use. Reusing industrial land for computing is a genuinely strong siting argument, and it is part of why the city voted yes unanimously while 40 of 41 speakers at the meeting opposed the deal. But reclaimed land does not come with reclaimed water rights: the aquifer underneath does not know the surface was mined. Land reuse solves the land question. It does not move the project one inch in the water queue.

What happens next — and what would change this briefing

The next verifiable event is a district action: an application filed, a governing-board agenda item, a permit issued, modified, or denied. Until one of those appears in a district record, the accurate status is the one in this briefing's headline — still waiting. What would change this briefing: (1) the district issuing or denying the modified consumptive use permit, which would replace "pending" with a permitted quantity and conditions; (2) a filed application stating a water figure different from 50,000 gallons a day, which would retire the estimate; (3) a court ruling on the reported lawsuits challenging the city's approval, which could reopen the land track as well. When any of those lands, this briefing stays as the record of November 22, 2026, and the data center guide carries the update.

Sources