Florida's New Data Center Water Law (SB 484), in Plain Words

Since July 1, 2026, a large data center in Florida can be refused its water permit outright — not delayed, refused — if its water use would be harmful to the water resources of the area. Here is what the law actually says, who it covers, and where its limits are.

Dark water surface, abstract texture
Illustrative texture image from the site library — never evidence for a claim, a listed business's work, a product, or a measurement.
← Latest briefings

Latest briefing — Saturday, November 21, 2026

Key point: Senate Bill 484 (SB 484), now Chapter 2026-65 of the Laws of Florida, created a new section of Florida water law — section 373.262 of the Florida Statutes — that governs water permits for large-scale data centers. A water management district or the Florida Department of Environmental Protection (DEP) may not issue a consumptive use permit (CUP) — the permit that authorizes withdrawing water from an aquifer or a river — to a large-scale data center if the proposed use is harmful to the water resources of the area, or if the project is prohibited by the local government's zoning regulations and comprehensive plan. When reclaimed water (treated wastewater, cleaned for reuse) is available at the property line and five conditions are all met, the district must require the data center to use it instead of fresh surface water or groundwater. The Governor approved the bill on May 7, 2026, and the water provisions took effect July 1, 2026.

First: what counts as a "large-scale" data center

The whole water law turns on one definition, in section 373.203 of the Florida Statutes. A data center is a facility that primarily contains electronic equipment used to process, store, and transmit digital information — either a free-standing structure, or a facility inside a larger structure with its own environmental controls. A large-scale data center is a single location with a data center on site whose anticipated monthly peak electrical load is 50 megawatts or more, calculated as the highest average load over a 15-minute interval.

Three details in that definition do real work. First, the line is drawn on electricity, not water: 50 megawatts of peak load is roughly the demand of a small city, and a site that big is the class of facility whose cooling can move an aquifer. Second, the load cannot be added up across multiple locations owned by the same customer to reach the line — but every tenant sharing one location under a colocation (shared-building) agreement counts toward that location's total, so a building full of smaller tenants is still large-scale if the building's peak clears 50 megawatts. Third, a customer may not split one site's electrical load into several smaller connections to duck under a related threshold in the law's power sections. Below 50 megawatts at one location, this water law does not apply at all — a smaller data center goes through the ordinary permit process like any other business. For how much water facilities of different sizes actually use, see the full guide: How much water does a data center use?

The two grounds on which a water permit must be refused

Section 373.262(2) gives two independent reasons a district or the DEP may not issue the permit:

The same subsection states the other side of the rule just as plainly: a permit shall be issued if the applicant establishes all three parts of Florida's long-standing permit test — (1) the use is a reasonable-beneficial use, as defined in section 373.019; (2) it will not interfere with any presently existing legal use of water; and (3) it is consistent with the public interest. So the law is not a ban. It is a gate with the test written on it: pass the three-part test and stay clear of the two refusal grounds, and the permit issues; fail, and for the first time a Florida data center's water can be stopped at the permit counter on harm grounds alone. The permit system behind all of this — who may pump, how much, and who decides — is explained in Who owns the water?

Reclaimed water: required, but only when five conditions all line up

Section 373.262(3) is the part of the law most often described loosely, so here it is exactly. The district or the DEP shall require — must require, not merely may require — the use of reclaimed water in place of all or part of a large-scale data center's proposed surface water or groundwater use, when all five of these are true:

Read the second condition closely, because it is where the rule's reach is set: the reclaimed-water main must already reach the property line. Where no utility has built reclaimed lines to the site, the mandate does not bite — the law does not order anyone to build the pipe. That is the honest limit of the provision, and it is also what makes reclaimed water the hinge of the whole law: the wastewater utility that extends a reclaimed main to an industrial area is, from that day on, the supplier a large data center may be required to buy from. Reclaimed water stops being only an irrigation product and becomes an industrial water supply.

The paperwork bar: full water accounting, a conservation plan, and a hearing

For any large-scale data center application asking for an average daily flow of 100,000 gallons of water per day or more, section 373.262(4) adds two requirements on top of the normal application rules in section 373.229. The application must itemize all sources and amounts of water, and all losses of water, used for cooling, for industrial and treatment processes, for employees' personal and sanitary needs, and for landscape irrigation. And it must include a water conservation plan that, at a minimum, recycles cooling water before discharge or disposal, runs a leak detection and repair program, uses water-efficient fixtures, and runs an employee awareness and education program on water conservation.

Then the procedural change that may matter most in practice: notwithstanding the usual rule that lets some applications be approved without one, the district or the DEP may not approve a large-scale data center's permit application without a hearing. Every approval gets a public proceeding. And if a permitted large-scale data center later wants to change its permit, section 373.239(2), as amended by this law, treats that modification application the same way as an initial application — there is no quiet amendment path around the hearing and the test.

For scale: the 100,000-gallon-a-day disclosure line is twice the roughly 50,000 gallons a day reported — as an estimate, not a permit figure — for the proposed Fort Meade campus in Polk County, whose Southwest Florida Water Management District (SWFWMD) water permit was still pending at last report. A campus at that reported size, if it qualifies as large-scale on the power test, would face the hearing and the harm test even below the extra-disclosure line. The regional stakes are in the scarcity guide: Is Florida running out of water?

The rest of the law, in one pass

SB 484 is wider than water, and three of its other pieces explain the water piece. On power costs, new section 366.043 requires public utilities to set minimum tariff and service requirements so that each large load customer bears its own full cost of service — connection, added transmission and generation, operations — with the cost and the risk of nonpayment kept off the general body of ratepayers; each public utility had to file a complying tariff with the Florida Public Service Commission (PSC) by October 1, 2026. On local control, section 163.326 keeps comprehensive planning and land development regulation of large load customers with local governments, and provides that a large load customer may not be treated as an electric substation. On transparency, the law removes data centers from an exception that let economic development agencies extend confidentiality for project information by an extra 12 months. Finally, the Office of Program Policy Analysis and Government Accountability (OPPAGA) — the Legislature's own research office — must contract for an independent study of large-scale data center construction and operation, covering land, water, energy, and cost impacts, and deliver it to the Governor, the President of the Senate, and the Speaker of the House by July 1, 2027. That study is the law's own built-in second look.

What the law does not do — and what would change this reading

It does not ban data centers, large or small, anywhere in Florida. It does not set a gallon cap, a cooling-technology mandate, or a statewide water budget for the industry. It does not touch data centers under the 50-megawatt line, farms, bottlers, or any other water user — they remain under the ordinary Chapter 373 permit system described in Tampa Bay permits and the ownership guide. And as of this briefing, no denial of a data center water permit under section 373.262 has been verified — the provision has been law for under five months, and its first real test will be a contested application, not a press release. What would change this briefing's reading: a district rule or court decision narrowing the phrase "harmful to the water resources of the area," the OPPAGA study's findings in 2027, or the first permit decision — grant or denial — that puts section 373.262 to work. When one lands, this briefing stays as the record of the law as written, and the linked guides carry the update.